CHPP Kenog Nova Gorica

In the Boiler House Kenog Rudis realized installation of the Combined Heat and Power Plant for combined heat and power generating with high efficiency.

CHPP during operating at maximum load generates 1,030 kW of electrical energy and 1,014 kW of thermal energy.

Employer:
E3, d.o.o. Nova Gorica
Completion date:
2007
Scope of works:

Supply and assembly of mechanical and electrical equipment, computer supervisory system, testing and commissioning, elaboration of Operation and Maintenance Instructions for the plant, staff training.