CHPP 3 in Petrol Energetika PE Hrastnik
In the Heating Plant Hrastnik the Combined Heat and Power Plant was constructed for combined heat and power generating with high efficiency of CHPP3.
CHPP3 during operation at maximum load generates 600 kW of electrical energy and 654 kW of thermal energy.
Employer:
Petrol Energetika d.o.o.Completion date:
2011Scope of works:
Designing, supply and assembly of mechanical and electrical equipment, construction works, computer supervisory system, testing and commissioning, elaboration of Operation and Maintenance Instructions for the plant, staff training.