Construction of the new factory for production of special glass packaging in Hrastnik
For construction of the new factory for production of special glass packaging in Hrastnik Rudis elaborated the preliminary design, including investment outline scheme and preliminary design of the Plant with technological equipment and investment amount evaluation.
On the basis of the aforementioned preliminary design Rudis supplied and installed the complete technological equipment for furnace pre-silo, flue gas treatment, shards return system, cooling air, technological and soft water, natural gas and compressed air.
Employer:
Steklarna Hrastnik d.o.o.Completion date:
2005Scope of works:
Elaboration of preliminary design, project documentation and studies, construction of the Plant, supply and assembly of mechanical and electrical technological equipment.