Reconstruction – ecological rehabilitation of the Heating Plant Hrastnik
In the Heating Plant Hrastnik ecological rehabilitation of the Heating Plant was realized by Rudis and it meant passage from solid to gaseous fuels. In the scope of Heating Plant reconstruction Rudis installed the boiler LOOS, power 15 MW.
Employer:
Toplarna Hrastnik, d.o.o.Completion date:
1994Scope of works:
Elaboration of project documentation (building permit documentation, final design), demolition works on coal boilers, supply of gas boilers LOOS Austria, supply and assembly of mechanical and electrical equipment, commissioning and trial run.