Reconstruction of the Hydro-Power Plant Una Bihač, Bosnia and Herzegovina

In Bosnia and Herzegovina in the scope of reconstruction of the Hydro-Power Plant Una Bihač Rudis assumed designing as well as supply and assembly of four generators per 2.5 MV, including the excitation system and appurtenant equipment, on ‘turnkey principle’.

Employer:
JP Elektroprivreda, Bosna in Hercegovina
Completion date:
2001
Scope of works:

Designing, supply and assembly on ‘turnkey principle’, training of the Employer’s staff, commissioning, performance tests and trial run.