Refurbishment of hydro-mechanical equipment at the Peručica Hydro-Power Plant in Montenegro

In the scope of comprehensive reconstruction of the Hydro-Power Plant Peručica in Montenegro Rudis designed and realized, on ‘turnkey principle’, refurbishment of four turbines of Units, power 40 MVA, and two turbines of auxiliary Units for self-consumption of the HPP - 1 MVA per each, as well as new turbine governing system.

Employer:
Elektroprivreda Crne Gore A.D.
Completion date:
2008
Scope of works:

Designing and construction on ‘turnkey principle’: elaboration of project documentation, refurbishment of four turbines and supply of the governing system for six Units.