At the Gas Power Plant in Puconci works are in the final stage
Rudis has been constructing a Plant for energy utilization of the landfill gas at Non-Hazardeous Waste Dump Puconci
Works at construction of the Plant are in the final stage. At present execution of connections of the container motor-generator unit - for combined generating of 300 kW of power and 330 kW of heat from the landfill gas produced at non-hazardeous waste depositing - is in progress.
In October the trial run and training of the User’s staff in handling of the Co-generation Unit will take place. Rudis signed also the Contract for 10-year maintenance of the Unit.