Outer Arrangement of 600 MW Unit 6 in Thermal Power Plant Šoštanj
Upon the introduction into works, on first days of March Rudis started with the execution of civil engineering and finishing works for auxiliary facilities of Outer Arrangement of Unit 6 at Šoštanj Thermal Power Plant
In February this year Rudis signed with the Client Thermal Power Plant Šoštanj the Contract for Civil Works - Outer Arrangement of Unit 6. This is the last international tender as part of the construction of Unit 6 in Šoštanj TPP. The civil construction works will be performed by the company AGM Nemec. The contractual scope of works includes:
- Outer arrangement of Main Technological Unit and Cooling tower
- Arrangement of three-section crossing in front of the administration building
- Road construction works (Askerceva street and street Lokovica – Sostanj)