Rudis will implement reconstruction of Toplarna Hrastnik in Hrastnik

Two hot water high efficiency natural gas boilers and with fuel gas as reserve fuel, extra-light heating oil, will be installed, as well as a pellet boiler

In January this year, the investor Petrol d.d., Ljubljana entrusted the implementation of reconstruction in Toplarna Hrastnik to RUDIS.

Works will be completed until the beginning of heating season 2022/23.

Toplarna Hrastnik is currently operating with two cogenerations with total heat output 2.240 kW and electric power 2.160 kW with natural gas as energy source. With the objective of reducing greenhouse gas emissions, the investor wishes to implement partial transition to biomass heating system for the purpose of heating the city of Hrastnik, which requires extensive reconstruction works in Toplarna.

 

During reconstruction, RUDIS will remove existing boiler plants, both CHP plants and other technical equipment. Two hot water high efficiency natural gas boilers and with fuel gas as reserve fuel, extra-light heating oil, will be installed, as well as a pellet boiler. A cogeneration plant with heat output 1.837 kW and electric power 1.840 kW and all other equipment, necessary for undisturbed operation of the district heating system will also be installed in the boiler house.

 